Ask each supplier to quote the same finished result
Start with the property location, intended residential use, finished interior area, room arrangement and finish level. Identify whether you want a shell, parts for assembly or a building with specified work completed in a factory. Share the same drawings and requirements with each bidder.
Record the site facts already established and label the rest as assumptions. A proposal based on an accessible, serviced property cannot be compared directly with one that includes new utility connections and difficult unloading. Keep land acquisition visible as its own budget item.
Build the budget around work, not just the package
For each item, state what work is needed, who does it and whether it has been priced. Count it once, even if several contractors discuss it.
| Budget item | What to define | Evidence to request |
|---|---|---|
| Design and review | Building design, engineering, revisions and site drawings | Written services and deliverables |
| Approvals and inspections | Required applications, reviews, inspections and associated charges | Current information from the relevant authorities |
| Building package | Container or other system, installed work and supplied parts | Itemised specifications and exclusions |
| Structure and envelope | Openings, reinforcement, insulation, air and water control, roof and windows | Project drawings and installation scope |
| Building systems | Electrical, plumbing, heating, cooling and ventilation | Equipment, installation, connections and testing scope |
| Site and foundation | Site assessment, preparation, supports and attachments | Site findings and a foundation proposal for this building |
| Water and wastewater | Available services or the proposed site system | Connection requirements and site assessment |
| Initial delivery and setting | Transport, unloading, placement and required equipment | Access assumptions and a written handling scope |
| Completion and closeout | Remaining finishes, testing, corrections and required records | A task list with assigned responsibility |
| Other project costs | Applicable VAT, charges and a separately identified reserve | Itemised amounts and the basis of any allowance |
Make proposals comparable before choosing one
Use one worksheet with a row for each task and a column for each proposal. Mark the task as included, separately priced, allowance, excluded or unknown. An allowance is a budgeting assumption; ask what it covers and how the final amount will be determined.
Ask for separate pricing on excluded work you still need. Resolve overlaps such as two parties charging for the same foundation connection. Keep unknown items open until a site finding or written proposal supplies the missing information; an unknown amount is not zero.
- Record the quote date, validity period, payment milestones and applicable charges.
- Check the finished area, equipment, materials and finish level against the shared specification.
- Separate factory work, transport, unloading, setting and work performed at the property.
- Identify who pays for design changes, inspection corrections and missing completion work.
- Price optional upgrades separately so the base proposals remain comparable.
Calculate the forecast without hiding gaps
Comparable construction forecast = building package + design and review + remaining building work + site and utilities + delivery and setting + completion and closeout + applicable VAT and mandatory charges. Include each task only once.
Total project budget = comparable construction forecast + land acquisition, if needed + your separately identified project reserve. State the basis of the reserve and keep it distinct from an allowance included in a contractor's proposal.
Label each amount as quoted, an allowance or unknown. A subtotal with unresolved items is a partial forecast. For a cost per m² comparison, divide comparable forecasts by the same defined finished interior area. A container's exterior footprint does not establish that area.
Resolve the property conditions that change the budget
Give the designer, installer and delivery provider the same site information. Foundation requirements, access and service connections need project-specific assessment. Confirm what is available at the property, where connections will run and which party will arrange the work.
Where septic service is proposed, the relevant local authority and environmental regulator and site assessment determine the requirements. Obtain the site findings and a proposal for the required work before treating wastewater as a fixed budget item.
Price the foundation against the actual building's support and attachment information. Price initial delivery against the actual transport dimensions, access and unloading plan. Include the review, testing and corrections required to finish each party's work.
Compare shell, kit and prefab routes at the same endpoint
Choose a route whose remaining work you can arrange and price. Compare the complete building, installation and site scope, with responsibility for each task identified.
| Starting point | What the proposal must identify | Work to account for |
|---|---|---|
| Container shell | Condition, dimensions and any structural or enclosure work supplied | Design, conversion, building systems, finishes and all site work |
| Home kit | Parts supplied, installed work, assembly instructions and exclusions | Missing materials, assembly, professional services and site work |
| Prefab package | Exact factory completion and the documents supplied with the building | Delivery, setting, foundation, site connections and remaining completion |
Prepare the details needed for an estimate
Select Container home / living space for Intended use and put the dwelling project in Project notes. Review the summary, then send it through the quote form with your consent, or copy or download it. Preparing or exporting the draft alone does not send it.
- Site location and status, with known access and utility findings.
- Intended residential use, target finished interior area, rooms and finish level.
- Proposed shell, kit or factory completion, with available drawings.
- Tasks to include, tasks you will arrange and items requiring assessment.
- Requested cost breakdown, estimates, exclusions and quote expiry date.
Buying questions
Does a listed container home price mean it is ready to occupy?
Read what the written offer includes: a shell, parts or specified factory work. List the design, site work, installation and finishing still needed. Check the requirements for using it as a home.
Can I compare proposals using cost per m²?
Yes, if both cover the same finished work and use the same definition of finished inside area. Show excluded and unknown costs beside the totals.
How should I handle an unpriced site item?
Mark it as unknown, identify who must assess it and request a separate proposal when the required information is available. Do not treat it as included or assign it a zero cost.
Check the UK project route
Check whether the property is in England, Scotland, Wales or Northern Ireland. Before committing to a unit, ask the local authority about its use, position, duration, size and site work. A movable container or short stay does not automatically remove the need for permission. Planning and building requirements are separate.
- England: planning permission guidance
- Scotland: development management
- Wales: planning permission
- Northern Ireland: planning permission
- England: Approved Documents
- Scotland: building standards and technical handbooks
- Wales: building regulations guidance
- Northern Ireland: building regulations
